Currently, the Ilesboro Road Reclamation Project is still being recontoured to ensure positive drainage. A bulldozer and scraper are being used to level out the high places and fill in the lower points with dirt. While some areas of the site are currently ready for resoil, it is expected that resoil, vegetation, and installation of …
The Contract completion date for the Daniels Reclamation Project is being extended to August 1, 2018 to allow for the remaining project work to be completed in more favorable weather and ground conditions. While most of the contracted work is complete, covering the spoil with resoil and revegetation activities have been slowed due to heavy …
The Ilesboro Road Reclamation Project site was cleared and the pits were drained, with water undergoing treatment as it drained. Currently, the contractors are working on recontouring the site. Check out these pictures below to see our progress! Click on the pictures to enlarge them.
Month: June 2018
Ilesboro Road Reclamation Project Update, 6-14-18
Posted: June 25, 2018 by Amy Mackey
Currently, the Ilesboro Road Reclamation Project is still being recontoured to ensure positive drainage. A bulldozer and scraper are being used to level out the high places and fill in the lower points with dirt. While some areas of the site are currently ready for resoil, it is expected that resoil, vegetation, and installation of …
Category: Project Updates
Daniels Run Reclamation Project Update, 6-7-18
Posted: June 25, 2018 by Amy Mackey
The Contract completion date for the Daniels Reclamation Project is being extended to August 1, 2018 to allow for the remaining project work to be completed in more favorable weather and ground conditions. While most of the contracted work is complete, covering the spoil with resoil and revegetation activities have been slowed due to heavy …
Category: Project Updates
Ilesboro Road Reclamation Project Update, 5-17-2018
Posted: June 1, 2018 by Amy Mackey
The Ilesboro Road Reclamation Project site was cleared and the pits were drained, with water undergoing treatment as it drained. Currently, the contractors are working on recontouring the site. Check out these pictures below to see our progress! Click on the pictures to enlarge them.
Category: Project Updates