Month: June 2018

Ilesboro Road Reclamation Project Update, 6-14-18

Currently, the Ilesboro Road Reclamation Project is still being recontoured to ensure positive drainage.  A bulldozer and scraper are being used to level out the high places and fill in the lower points with dirt.  While some areas of the site are currently ready for resoil, it is expected that resoil, vegetation, and installation of …

Daniels Run Reclamation Project Update, 6-7-18

The Contract completion date for the Daniels Reclamation Project is being extended to August 1, 2018 to allow for the remaining project work to be completed in more favorable weather and ground conditions.  While most of the contracted work is complete, covering the spoil with resoil and revegetation activities have been slowed due to heavy …