Ilesboro Road Reclamation Project Update, 6-14-18

Currently, the Ilesboro Road Reclamation Project is still being recontoured to ensure positive drainage.  A bulldozer and scraper are being used to level out the high places and fill in the lower points with dirt.  While some areas of the site are currently ready for resoil, it is expected that resoil, vegetation, and installation of the limestone channel will all go in this summer or fall.  Check out the pictures below to view our progress!